1 of 25
PROCESS
A sponsor asks the project manager to begin work on an unapproved change to protect a market date. What should the project manager do first?
Choose one answer
A
Ask the team to begin low-risk work
B
Assess the change and follow the agreed change approach
C
Refuse the sponsor's request
D
Add the work to the backlog without review